Aroor-Thuravoor Elevated Highway Gets More Time, Deadline Extended to March 2027
The 12.75-km-long Aroor-Thuravoor six-lane elevated highway, set to become India’s longest single-pillar flyover, is now facing delays. Its completion deadline has been extended from December to March 2027. Approximately 94% of the work is complete, and the National Highways Authority of India (NHAI) is set to begin load testing next week.
The primary reason for this delay is a last-minute design change near Thuravoor. To alleviate congestion, six additional spans, each approximately 150 metres long, are being added, extending the flyover beyond the busy junction to reach the Thuravoor temple. This additional work is expected to take another three to four months.
Furthermore, Kerala’s first multi-lane free-flow toll system will be implemented at Eramalloor, allowing vehicles to pass through without stopping at a toll booth. Overhead scanners will automatically identify the vehicles and deduct the toll charges from their FASTag accounts.
Additionally, following several incidents, such as wall collapses, land subsidence, and structural failures in areas like Mylakkadu, Kuriad, and the Ramanattukara-Valanchery stretch, IIT Palakkad has begun an investigation into the 'reinforced soil walls' constructed along NH-66.