Advanced Formworks for High-Rise Buildings and Tall Structures
Vertical development is the
ideal solution to meet the demand of land for the fast growing urban population
globally and in India. It is the construction of tall structures such as
high-rise buildings, sky scrapers and sky towers etc., rather than constructing
laterally to accommodate large population in quiet a lesser area. However the
construction of high-rise buildings are highly complex and requires advanced
construction techniques and equipment. One of the most important requirements
is the advancement in forming technology. Though the conventional or
traditional method of forming high-rise building is economical, it suffers
seriously on the time, quality, safety and sustainability factors. Therefore,
the advanced systems of formworks known as climbing formwork, slip-form
formworks, Tunnel formworks etc. were introduced later.
Formwork is unquestionably
important in any construction; its fundamental benefit is that it cannot be
substituted by any other technology. Concrete structures can be built rapidly
and at a low cost by employing formwork. A formwork provides suitable access
and working platforms throughout the construction process, significantly
improving worker’s safety, employees' safety & also scaffold safety.
By reducing the
floor-to-floor building cycle time, formwork aids in the reduction of project
timelines and costs, allowing more projects to meet their budgetary
requirements. Formwork enables construction managers to provide precise on-time
shuttering and de-shuttering of formwork resources, resulting in increased
project efficiency and resource utilisation.
Climbing
formwork
Climbing formwork, also
known as jumpform, is a special type formwork for vertical concrete structures
that rises with the building process. While relatively complicated and costly,
it can be an effective solution for buildings that are either very repetitive
in form (such as towers or skyscrapers) or that require a seamless wall
structure (using gliding formwork, a special type of climbing formwork).
Best known in the
construction of towers, high-rise buildings and other tall vertical structures,
it allows the reuse of the same formwork over and over for identical (or very
similar) sections / storeys further up the structure. It can also enable very
large concrete structures to be constructed in one single pour (which may take
days or weeks as the formwork rises with the process), thus creating seamless
structures with enhanced strength and visual appearance, as well as reducing
construction times and material costs (at the joints which would otherwise
require extra reinforcement / connectors).
The climbing formwork
structure normally does not only contain the formwork itself, but also usually
provides working space / scaffolds for construction crews. It may also provide
areas for machinery and screens for weather protection, up to being fully
enclosed while yet staying modular around a changing building structure.
Various types of climbing
formwork exist, which are either relocated from time to time (generally with
crane), or can even move on their own (usually on hydraulic jacks, required for
self-climbing and gliding formworks).
Crane-Climbing Formwork: in
this type of climbing formwork, the formwork around the structure is displaced
upwards with the help of one or more cranes once the hardening of the concrete
has proceeded far enough. This may entail lifting the whole section, or be
achieved segmentally.
Self-Climbing Formwork
In
this type of formwork, the structure elevates itself with the help of mechanic
leverage equipment (usually hydraulic). To do this, it is usually fixed to
sacrificial cones or rails emplaced in the previously cast concrete. Self-climbing
formwork is an automatic climbing system that is lifted without using a crane.
Instead, it has hydraulic rams that lift the scaffold, formwork, and secondary
formwork to the next pouring cycle. Since self-climbing formwork does not
require any lifting equipment, it can significantly help reduce overall costs
and labour. Another advantage is that it allows builders to continue their work
even when it is very windy.
Gliding Formwork
This type
of formwork is similar to the self-climbing type above. However, the climbing
process is continuous instead of intermittent, and is usually only interrupted
for a very short time (for example to fix the mounting mechanisms to new
anchoring points). The advantage is that it will produce seamless structures,
but it requires a continuous, uninterrupted process throughout, with serious
potential quality and stability problems if the pour has to be stopped.
Slipform
Formwork
Slipform construction
technique has been gaining a lot of popularity over the years in the construction
of high-rise buildings because of the many advantages it has to offer.
Slipform construction
technique is normally adopted for the centrally located service core of a
high-rise building. The service core or simply core of a high-rise building is
normally located at the central portion of the building which hosts facilities
not meant for dwelling or renting purposes but for common uses of all the
occupants or users of the building and are integral parts of any such building.
These include the elevator shafts, public restrooms or toilets, ventilation
& electrical shafts, stairwells etc.
There are several reasons
of slipform construction being economical for tall buildings or structures. The
key reason is the repetitive nature of the method itself. Once installed, the
formwork need not be dismantled and reinstalled again for further use. The same
setting continues till the job, in this case the core structure of a high-rise,
is complete. Even in the case of a very tall building where the core is sometimes
reduced abruptly at certain elevations for various reasons, change in settings
of the slipform structure need to be done only at those few particular
elevations. This results in saving a great deal of time, manpower as well as
materials and thus becomes more economic than conventional methods. The method
of construction requires a much smaller group of highly skilled workers as
compared to other usual methods including jump-form method. It also needs
lesser quantity of forms.
The starter walls, meant
for commencing installation of slipforms, must have all the necessary
embedments/provisions including the jack-rods on which the entire slipform unit
would climb up. The walls also must have all the vertical reinforcing steel
bars with adequate projections.
This entire unit consisting
of the slip-forms, cross-beams, platforms etc. are raised in synchronisation
along the jack rods by means of hydraulic jacks of suitable capacities. The
jack rods, which are usually embedded in the concrete walls of the core itself,
can be either sacrificed or removed later on if so planned.
Besides fixing re-bars,
these platforms are also used for fixing doors and window frames,
inserts/embedments, keeping provisions for supports and other openings and so
on.
Lowermost platform is used
mostly for quality related purposes such as monitoring concrete quality,
continuous surface finishing of freshly stripped concrete surfaces, curing,
rectification of shortcomings, if any, and so on.
The rate of lifting of
forms primarily depends upon the rate of setting of the poured concrete. The
lowermost portion of the poured concrete inside the slipform must set
sufficiently in order to gain enough strength to support itself as well as the
layers above it (upto the top of forms) without getting deformed/damaged while
the forms are slipped up. At the same time, it should not set too hard and thus
resulting in excessive friction between the forms and the concrete surface.
That could lead to difficulties in lifting the forms which in turn could damage
the still-fresh surface of the concrete as well.
Tunnel
Formwork
Tunnel form is a formwork
system that allows the contractor to build monolithic walls and slabs in one
operation on a daily cycle. It combines the speed, quality and accuracy of
factory/offsite produced ready-mix concrete and formwork with the flexibility
and economy of cast in-situ construction. Tunnel formwork system is one type of
construction techniques used for multi storied building construction to reduce
cycle time. Its usefulness also stems from the fact that no starter concrete is
required for walls; it allows easy alignment and de-shuttering, hot air curing
to enable early stripping and favours a standardized working sequence to
improve labour productivity.
A recent trend in the building industry in India, as well as in many countries with increasing city populations, is toward utilizing the tunnel-form (shear wall) construction system for development of multi-storey residential units. This has been driven basically by the need to construct earthquake resistant multi-storey reinforced concrete (RC) buildings with considerable ease, speed and economy. The tunnel-form system is an industrialized construction technique in which structural walls and slabs are cast (in situ) simultaneously using steel forms composed of vertical and horizontal panels set at right angles. To expedite the construction, non-structural components such as facade walls, stairs and chimneys are commonly produced as prefabricated elements. Tunnel-form buildings generally have a symmetrical configuration in horizontal and vertical planes that enables continuous flow of construction and better quality assurance. Besides the constructive advantages, tunnel-form buildings provide superior seismic performance compared to conventional RC frame and dual systems, which suffered significant damage and total collapse in many regions during devastating earthquakes in India.